SC1C (TOU)- All Zones Delivery
Niagara Mohawk Power Corp. · Time-of-use · filed 2025
$0.0782per kWh, all in
$938a year at 1,000 kWh/mo
$30.62fixed, before any usage
$0.1667utility's actual average
What this tariff charges
| Fixed charge | $30.62 per month |
|---|---|
| Structure | Time-of-use |
| Filed | 2025-01-30 |
Energy rates
The charged price is the base rate plus its adjustment. Adjustments carry fuel and rider costs and are frequently most of the bill, so a comparison built on the base rate alone is meaningless.
Period 0
| Tier | Up to | Base | Adjustment | Charged $/kWh |
|---|---|---|---|---|
| 1 | no limit | 0.04068 | 0.00688 | 0.04756 |
Period 1
| Tier | Up to | Base | Adjustment | Charged $/kWh |
|---|---|---|---|---|
| 1 | no limit | 0.04068 | 0.00688 | 0.04756 |
Period 2
| Tier | Up to | Base | Adjustment | Charged $/kWh |
|---|---|---|---|---|
| 1 | no limit | 0.04068 | 0.00688 | 0.04756 |
What it costs at different usage levels
| kWh per month | Annual total | Effective $/kWh |
|---|---|---|
| 500 | $652.80 | $0.1088 |
| 1000 | $938.16 | $0.0782 |
| 2000 | $1,508.88 | $0.0629 |
Effective rate includes the fixed charge, which is why it falls as usage rises. This is a time-of-use tariff, so the result also depends on when power is used; an average residential pattern is assumed. Details →
The utility's own description
Load Zone A applies to the West/Frontier Region. An Income Eligible Basic Service Credit of $5.00 or $15.00 (for Electric Heat Customers) may apply. Customers served under this service classification may be subject to adjustments and applied in the manners described in each respective Rule. *Rule 32.2 - Municipal Undergrounding Surcharge *Rule 41 -System Benefits Charge *Rule 42 -Merchant Function Charge *Rule 43 -Transmission Revenue Adjustment *Rule 46- Supply Service Charges *Rule 49 -Renewable Portfolio Surcharge *Rule 50 - Reliability Support Services Surcharge *Rule 56 - Incremental State Assessment Surcharge *Rule 57 - Revenue Decoupling Mechanism *Rule 58 - Temporary Rate Adjustment Mechanism *Rule 59 - Temporary Deferral Recovery Surcharge/Credit